MY HOME

TOTAL 6 BEAMS
BELTS IS DONE ON THE BASEMENT NOT ON THE "THARA".
ALL BASEMENT AND "THARA" WORKS ARE DONE WITH ACC CEMENT NOT USING CLAY.
FOUR BEAMS AT FOUR CORNERS OF THE BASEMENT.
THE STAIR ROOM DOOR IS IN BETWEEN TWO BEAMS.(THE BEAMS ARE AT THE END POINTS OF THAT SIDE)
ALL BRICKS ARE "ARACHA KATTA" FROM KUZHALMANNAM.
99% PART OF THE CEMENT IS ACC AND REST IS MALABAR CLASSIC.
ALL WATER PIPES ARE ISI MARKED PIPES(STAR PIPE)
WATER TANK IS ISI MARKED TANK
ALL TAP CONNECTORS ARE BRASS
TILE IS STAIN FREE VITRIFIED(JOHNSON'S MARBONITE)
PAINT IS ASIAN CEMENT PRIMER.
WORK AREA TILE-REGENCY
BATHROOM FLOOR TILE-BELL
SINK IS MAYUR STINLESS STEEL
DOOR PAINT IS MAHAGONY-ASIAN
WINDOW BLACK PAINT-ASIAN
ALL BATHROOM ARE READY FOR ADDING HEATER-SEPARATE PIPES ARE PROVIDED FOR THAT(CVPC)
EARTHING IS DONE WITH SALT(25 PACKS),"KARI" AND SAND-BHARATHAPUZHA
THE LENGTH OF THE EARTHING RODS ARE 4 FEETS
THE COPPER WIRE USED FOR EARTHING HAVE 10MM GAUGE WITH HIGH LEVEL THICKNESS.(OR 8MM)
99% WORKS ARE DONE USING GOOD SAND.